Premier Christy Clark and BC Hydro CEO Jessica McDonald at announcement to proceed with Site C dam on the Peace River, 2015. (BC GOVERNMENT)

Premier Christy Clark and BC Hydro CEO Jessica McDonald at announcement to proceed with Site C dam on the Peace River, 2015. (BC GOVERNMENT)

$1.75 billion spent on Site C so far

BC Hydro details risks of delay with $60 million a month being spent

The Site C dam project in northeastern B.C. has spent $1.75 billion as of the end of May and is currently spending $60 million a month, BC Hydro CEO Jessica McDonald says.

McDonald and other BC Hydro executives briefed reporters Wednesday on the project, after an exchange of letters Tuesday between Premier Christy Clark, NDP leader John Horgan and B.C. Green Party leader Andrew Weaver.

McDonald provided details on Clark’s estimate that a delay in relocating two houses on the site on the Peace River near Fort St. John would create a “domino effect,” delaying construction of a realigned road and bridge that would lead to a one-year delay in diverting the Peace River to begin work on the dam foundation in the riverbed.

BC Hydro estimates show that delay would add $630 million to the cost of the project, including storage of turbines and generators, an additional year of site and environmental maintenance, and shutting down and restarting the main civil works contract.

McDonald said there is $4 billion spent or committed in existing contracts for the third dam on the Peace River, a system that already supplies a third of B.C.’s hydroelectric power. She would not comment on eventual costs of cancelling the project.

Horgan wants the Site C dam put to a review by the B.C. Utilities Commission. He said during the election campaign that does not mean stopping the project while the review goes ahead. After the minority government result and Weaver’s decision to support an NDP government, Horgan wrote to BC Hydro asking it to stop issuing new contracts and extend the lease on two houses set to be moved.

Weaver campaigned to have the project stopped. He attended the briefing at a Victoria hotel Wednesday, and said afterward the $4 billion cost estimate is a “gross exaggeration” based on the assumption all contracts would be paid out in full.

McDonald wouldn’t comment on the scenario of cancelling the $8 billion project, which she said is a political decision. Her presentation detailed the fallout from delaying the relocation of two houses for realignment of Highway 29 along the Peace River, a project about to be tendered by the B.C. transportation ministry.

The house properties have been expropriated and if they are not moved to make room for the two-year road and bridge construction, that would trigger a one-year delay in the river diversion needed to build the dam foundation in the main channel of the river.

BC Election 2017BC Hydro

Be Among The First To Know

Create a free account today, and start receiving free newsletters.

Sign Up with google Sign Up with facebook

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Reset your password

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

A link has been emailed to you - check your inbox.



Don't have an account? Click here to sign up
Pop-up banner image