Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Stabbing at Surrey banquet hall sends man to hospital

RCMP says victim has ‘non-life threatening’ injuries, incident still under investigation

55-year-old man taken to hospital after fire at Surrey RV park

Firefighters find man suffering from smoke inhalation, burns to face and hands: battalion chief

South Surrey parking ticket perplexes, frustrates

Theresa Delaney predicts more people will be wrongly ticketed

OUR VIEW: Let’s find Surrey pellet-gun punks

Those who do have information – if they are also possessed of a conscience – must contact police

Coldest Night an event for warm hearts

Sources’ White Rock event one of 130 walkathons across Canada on Feb. 23

B.C. students win Great Waters Challenge video contest

Video, mural and song about saving the salmon claims the top prize

Ammonia leak shuts down curling club in Nelson

It’s not yet clear when the leak was detected

Pavelski’s 31st goal helps Sharks top Canucks 3-2

Vancouver one point out of second NHL wild-card spot

Eight cases of measles confirmed in Vancouver outbreak

Coastal Health official say the cases stem from the French-language Ecole Jules Verne Secondary

Ontario police field complaints over Amber Alert for missing girl, 11, found dead

Some said the Amber Alert issued late Thursday for Riya Rajkumar disrupted their sleep

Former B.C. premier Gordon Campbell accused of sexual touching

Accuser went to police, interviewed by Britian’s Daily Telegraph

B.C. couple attacked with acid, slashed with knife in Vietnam

Warning, graphic images: Man has burns on 80 per cent of his body, slashed with knife

Northern B.C. First Nation clan says ancient tools found at pipeline work site

Archeologists from the Smithsonian Institute estimate one of the stones found dates back up to 3500 years

Most Read