Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Stabbing at Surrey banquet hall sends man to hospital

RCMP says victim has ‘non-life threatening’ injuries, incident still under investigation

55-year-old man taken to hospital after fire at Surrey RV park

Firefighters find man suffering from smoke inhalation, burns to face and hands: battalion chief

Slam poetry creates catharsis for North Delta youth

Burnsview Secondary team gearing up for poetry festival and competition in April

‘Just like Iron Man’: Calgary surgeon undergoes experimental spinal surgery

Dr. Richi Gill was in a freak accident on a boogie board during a family vacation in Hawaii

Deported B.C. man who came to Canada as a baby granted chance at return

Lee Van Heest was deported to the Netherlands in 2017

A Mother’s Wish: Ryan Shtuka’s mother wants her son to be ‘forever known’

‍‍‍‍‍“Let me tell you a story …. it all began with a boy named Ryan”

Sex abuse survivors to meet with Vatican summit organizers

Pope Francis has urged participants to meet with abuse victims before they came to Rome

Ex-FBI official: ‘Crime may have been committed’ by Trump

Andrew McCabe said FBI had good reason to open a counterintelligence investigation into whether Trump was in league with Russia

B.C. athlete takes home gold in freestyle aerials at Canada Games

Brayden Kuroda won the event with a combined score of 121.65.

Pedestrian in serious condition after hit by car downtown Abbotsford

A youth was also hit, suffered minor injuries, police say

Most Read