Builder of Kinder Morgan reinforces concerns over project

B.C. heads to court over pipeline jurisdiction as builder says doubt warranted

British Columbia has announced it will head to court by month end to clarify the province’s jurisdiction over the Trans Mountain pipeline expansion project.

Also Wednesday, the CEO of the pipeline’s builder, Kinder Morgan said the events of recent days have reinforced his concerns about the viability of the $7.4-billion project.

Steve Kean said during an earnings report that the company suspended work on non-essential activities earlier this month because the investment may be “untenable for a private party to undertake,” and recent days have “confirmed” those views.

The construction project has been the subject of growing friction, with Prime Minister Justin Trudeau summoning the premiers of Alberta and B.C. to Ottawa for talks and Alberta introducing legislation designed to restrict fuel shipments to B.C.

RELATED: Last-ditch pipeline court challenge going ahead

Kinder Morgan set a May 31 deadline to determine if the expansion will go ahead, prompting Trudeau’s Liberals to start private, financial talks with the U.S.-based company.

Premier John Horgan said his New Democrat government’s reference case will be filed in B.C.’s Court of Appeal by April 30 and it will seek to clarify the province’s rights to protect its coast and economy from an oil products spill.

He said the reference case could have implications in provincial-federal relations that go beyond the current dispute.

“We believe we have jurisdiction to protect the interests of British Columbians,” Horgan said at a news conference to announce government housing development initiatives.

“Our neighbouring province disagrees with that, the federal government disagrees with that,” he said. “In my conversations with the prime minister over the weekend he said, ‘Why can’t we work this out now? ‘ I said, ‘That’s fine, you and I can work this out but what about the next government in Ottawa or the next government in Victoria and on and on and on?’ “

Horgan also raised concerns about Indigenous rights over the project. More than 30 First Nations along the pipeline route have agreements with the company, but others are in opposition.

“I just reject the notion that this is a majority-rule situation,” he said. “These are rights and title holders and those rights and title holders have to be acknowledged and have to be respected.”

Jim Carr, federal Natural Resources Minister, said the government in Ottawa is looking to introduce legislation to reassert Canada’s constitutional authority to build and expand pipelines.

The federal government has repeatedly rejected B.C.’s invitations to join the reference case, saying it already has authority over pipelines.

B.C. Environment Minister George Heyman said Wednesday the province believes it has the right to protect its environment and economy from an oil products spill.

“The process is about B.C.’s right under the Constitution to regulate against the deleterious impacts on the environment, on the economy, on provincial interests of a project, whether it’s an interprovincial project or a provincial project.”

RELATED: Poll finds 54% of B.C. residents support Trans Mountain

Attorney General David Eby said the province will take its case to the B.C. Court of Appeal, the highest court that it is able to refer such questions under the province’s Constitutional Question Act.

The details of the action and the question or questions the government will ask the court to determine are still being worked out by lawyers and must be approved by the New Democrat government’s cabinet, he said.

Eby said the province is aware of the time factors involved and is hopeful of a speedy ruling.

“Everybody wants clarity around this so we’ll be moving and we are moving as quickly as we can,” he said.

Alberta’s government said B.C.’s legal move is just another pipeline roadblock.

Alberta Energy Minister Marg McCuaig-Boyd said the law around the issue has already been settled and that it’s clear the federal government has the final say on interprovincial pipelines.

“They (the B.C. government) continue to play political games,” she said.

“They continue to try to frustrate investors (and) erode investor confidence, but what I can say is we are prepared to pull the rug out from under them.”

RELATED: Pipeline protest greets Trudeau in England

She said the rug allusion refers to ongoing talks with Alberta and the federal government to buy into the pipeline project to ensure it gets completed.

Saskatchewan Premier Scott Moe said his province is preparing to introduce oil restriction legislation similar to Alberta’s, which is likely to send fuel prices in B.C. sky high.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

South Surrey Spirit Garden to host Solstice Stroll

Candlelight event to begin at 8 p.m. June 22

The struggle for space inside Surrey’s elementary schools

SECOND IN A SERIES: A look at how overcrowding impacts student life

VIDEO: 5X Festival takes over Surrey’s Central City plaza

Second annual event draws thousands of people throughout the day

Semiahmoo First Nation opens cannabis dispensary

Indigenous Bloom partners with First Nations

City shifts proposed transit station to King George after cancellation of LRT

Council to consider Newton Town Centre plan in fall

10 facts about Father’s Day

Did you know that the special day for dads was first celebrated in 1910?

Parents of BC murder victim want personal belongings returned

Lisa Dudley’s parents, Rosemarie and Mark Surakka, were at the Mission RCMP detachment Sunday

B.C. VIEWS: When farmland protection doesn’t protect farmers

Secondary residences aren’t mansions, families tell Lana Popham

Bombers down B.C. Lions 33-23 in season opener

Former Lion Andrew Harris leads Winnipeg with 148 rushing yards

Northern B.C. family remembers murdered Indigenous woman with memorial walk

Still no closure for Ramona Wilson’s family 25 years later

Pride flag taken down by Township of Langley

Woman said she was told it was removed from her front yard because of a complaint

B.C. university to offer mentorship program for former youth in care

Students using the provincial tuition waiver program will soon be able to form a community at KPU

Cyclists competing in one of the toughest bike races on the planet pass through Fernie

Divide riders looking strong as they finish first leg of 4160 km race

You might not know these B.C. records are public

Hired a lawyer to file a civil claim? Those are published online

Most Read