Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

Surrey celebrates multiculturalism with annual Fusion Festival

The two-day festival returns to Holland Park

RCMP investigate two shootings in Surrey

Incidents happened in Whalley, Newton

Surrey Board of Trade fears SkyTrain expansion will impede other transit needs

‘We need transit improvements in all of Surrey,’ Anita Huberman says

Public hearing set for two Surrey modular housing projects for homeless

Surrey council set to vote Monday on projects in Guildford, Whalley

Rich the Vegan scoots across Canada for the animals

Rich Adams is riding his push scooter across Canada to bring awareness to the dog meat trade in Asia

Canadian high school science courses behind on climate change, says UBC study

Researchers found performance on key areas varies by province and territory

UPDATE: One dead after house fire in rural Maple Ridge

Dewdney Trunk Road closed, traffic being re-routed

Six inducted into BC Hockey Hall of Fame

The 26th ceremony in Penticton welcomed powerful figures both from on and off the ice

Highway 1 closed near Revelstoke

No estimated time for opening

CRA program to help poor file taxes yields noticeable bump in people helped

Extra money allows volunteer-driven clinics to operate year-round

Recall: Certain Pacific oysters may pose threat of paralytic shellfish poisoning

Consumers urged to either return affected packages or throw them out

How a Kamloops-born man helped put us on the moon

Jim Chamberlin did troubleshooting for the Apollo program, which led to its success

Most Read